Fukushima Daiichi: What happened in the first few hours after the earthquake and tsunami ?

A magnitude 9 earthquake near Sendai occurred at 14:46 JST (05:46 UTC) on Friday, March 11. The subsequent tsunami hit Fukushima Prefecture about an hour later.  There has been very little information about what happened at Daini and Daiichi in the first hours after the earthquake and tsunami that hit the two plants. 

I first blogged about the earthquake and nuclear power plants in Japan 16:58 ET March 11 (06:58 am Saturday March 12 JST) or about 16 hours after the earthquake.  At that point it had been reported that after the earthquake stopped off-ste power at Daiichi, a backup generator also failed and the cooling system was unable to supply water to cool the Unit 1 reactor, although at least one backup cooling system was being used, and that the reactor core remained hot even after the shutdown.  TEPCO was reported to be bringing in mobile generators to restore the power supply.   Pressure inside the containment of Unit 1 was continuing to increase, so at this point TEPCO had lost the ability to control pressure in the Unit 1 reactor pressure vessel.  Pressure inside the reactor had risen to 1.5 times the level considered normal and the government announced that vapour would be vented from the unit, to lower the pressure in an effort to protect it from “a possible meltdown.”

March 12 TEPCO reported that the pressure suppresion function was lost at Daiini and it was preparing to vent vapour from the reactors, but that Units 1,2, and 4 retained off-site power.

There have been reports from TEPCO estimating the height of the tsunami that hit Daiini and Daiichi of 10 meters and 12 meters and later 14 meters.

But outside of that there has been very little information about what happened at Daini and Daiichi in the first hours after the magnitude 9 earthquake and the tsunami that hit the two plants.  March 13 I blogged about what WNN inferred had happened. According to NHK, “the plant’s operator, Tokyo Electric Power Company, has so far only disclosed data from the day after the quake.”

Unit 1

Friday, April 08, NHK has obtained “unreleased data” that shows that 7 hours after the earthquake and tsunami the water level inside the Unit 1 reactor dropped to 45 cm above the top of the fuel assembly, or about one-tenth the normal level,  and 11 hours after that the fuel rods become exposed.  According to Professor Naoto Sekimura of the University of Tokyo, the loss of cooling functions at the Unit.1 reactor followed by the exposure of the fuel rods may have led to the first hydrogen explosion March 12.

Units 2 and 3

At Units 2 and 3 emergency generators kept the water levels in the reactors 4 meters above the top of the fuel assembly. It was much longer, between a day and a half to 3 days before fuel rods in these reactors were exposed.

Geoff Zeiss

Geoff Zeiss

Geoff Zeiss has more than 20 years experience in the geospatial software industry and 15 years experience developing enterprise geospatial solutions for the utilities, communications, and public works industries. His particular interests include the convergence of BIM, CAD, geospatial, and 3D. In recognition of his efforts to evangelize geospatial in vertical industries such as utilities and construction, Geoff received the Geospatial Ambassador Award at Geospatial World Forum 2014. Currently Geoff is Principal at Between the Poles, a thought leadership consulting firm. From 2001 to 2012 Geoff was Director of Utility Industry Program at Autodesk Inc, where he was responsible for thought leadership for the utility industry program. From 1999 to 2001 he was Director of Enterprise Software Development at Autodesk. He received one of ten annual global technology awards in 2004 from Oracle Corporation for technical innovation and leadership in the use of Oracle. Prior to Autodesk Geoff was Director of Product Development at VISION* Solutions. VISION* Solutions is credited with pioneering relational spatial data management, CAD/GIS integration, and long transactions (data versioning) in the utility, communications, and public works industries. Geoff is a frequent speaker at geospatial and utility events around the world including Geospatial World Forum, Where 2.0, MundoGeo Connect (Brazil), Middle East Spatial Geospatial Forum, India Geospatial Forum, Location Intelligence, Asia Geospatial Forum, and GITA events in US, Japan and Australia. Geoff received Speaker Excellence Awards at GITA 2007-2009.

View article by Geoff Zeiss

Be the first to comment

Leave a Reply

Your email address will not be published.


*