Impact of Japan Earthquake on Nuclear Power Plants: Fukushima Daiichi and Fukushima Daini

Incidents stipulated in Article 15, Clause 1 of the Act on Special Measures Concerning Nuclear Emergency Preparedness have been reported by TEPCO for both Fukushima Daiichi and Fukushima Daini nuclear power plants.

This is the status of Fukushima Daiichi and Fukushima Daini Nuclear Power Plants as of 10:00 am March 12 Japan Time (08:00:00 p.m. Friday March 11 Eastern Time) reported by TEPCO.

Below is major impact to TEPCO’s facilities due to the Miyagiken-Oki
Earthquake that occurred yesterday at 2:46PM.
*new items are underlined

[Nuclear Power Station]

Fukushima Daiichi Nuclear Power Station:
  Units 1 to 3: shutdown due to earthquake
  Units 4 to 6: outage due to regular inspection
* The national government has instructed evacuation for those local
residents within 10km radius of the periphery.
* Measurement of radioactive material (Iodine, etc.) by monitoring car
indicates increasing value compared to normal level. One of the
monitoring posts is also indicating higher than normal level. We will
continue monitoring discharge of radioactive material from exhaust stack
and discharge canal, etc.
* Considering the increasing pressure with in the reactor containment
vessel of Unit 1, the national government has instructed us to
implement measures to reduce the pressure of the reactor containment
vessel (partial discharge of air containing radioactive materials) in
order to fully secure safety.

Fukushima Daini Nuclear Power Station:
  Units 1 to 4: shutdown due to earthquake
* The national government has instructed evacuation for those local
residents within 3km radius of the periphery and indoor standby for those
local residents between 3km and 10km radius of the periphery.
* At present, we have decided to prepare implementing measures to reduce
the pressure of the reactor containment vessel (partial discharge of air
containing radioactive materials) in order to fully secure safety.
These measures are considered to be implemented in Units 1 to 4 and
accordingly, we have reported and/or noticed the government agencies
concerned.

Geoff Zeiss

Geoff Zeiss

Geoff Zeiss has more than 20 years experience in the geospatial software industry and 15 years experience developing enterprise geospatial solutions for the utilities, communications, and public works industries. His particular interests include the convergence of BIM, CAD, geospatial, and 3D. In recognition of his efforts to evangelize geospatial in vertical industries such as utilities and construction, Geoff received the Geospatial Ambassador Award at Geospatial World Forum 2014. Currently Geoff is Principal at Between the Poles, a thought leadership consulting firm. From 2001 to 2012 Geoff was Director of Utility Industry Program at Autodesk Inc, where he was responsible for thought leadership for the utility industry program. From 1999 to 2001 he was Director of Enterprise Software Development at Autodesk. He received one of ten annual global technology awards in 2004 from Oracle Corporation for technical innovation and leadership in the use of Oracle. Prior to Autodesk Geoff was Director of Product Development at VISION* Solutions. VISION* Solutions is credited with pioneering relational spatial data management, CAD/GIS integration, and long transactions (data versioning) in the utility, communications, and public works industries. Geoff is a frequent speaker at geospatial and utility events around the world including Geospatial World Forum, Where 2.0, MundoGeo Connect (Brazil), Middle East Spatial Geospatial Forum, India Geospatial Forum, Location Intelligence, Asia Geospatial Forum, and GITA events in US, Japan and Australia. Geoff received Speaker Excellence Awards at GITA 2007-2009.

View article by Geoff Zeiss

Be the first to comment

Leave a Reply

Your email address will not be published.


*